By the time RWE brought forward proposals for Strawberry Solar Farm in 2025, several other schemes had already been proposed in the area. Local people were weighing up the need for renewable energy against the cumulative impact on the landscape and the loss of agricultural land. There was also a degree of consultation fatigue.
Strawberry Solar Farm would generate enough electricity to power around 18,500 homes each year. The proposals also included significant biodiversity improvements and a £500,000 community benefit fund. But demonstrating those benefits in an area where opposition was already well established needed careful handling.
Fortunately, we weren’t starting from scratch.
Our previous work on nearby solar projects meant we knew Congresbury and understood the local sensitivities. Just as importantly, we had established relationships with the local ward councillor and Parish Council. That familiarity allowed us to approach the proposals with an understanding of the local context and have frank discussions about the issues likely to arise.
We contacted 2,133 local households and businesses, organised a public exhibition and presented the proposals to Congresbury Parish Council. Alongside this, we reviewed and helped write content for RWE’s dedicated consultation website and managed enquiries through a Freephone service and email.
The feedback made clear that not everyone was convinced. Of the 38 respondents who answered the question about support for the scheme, 29 were opposed. But consultation isn’t just about counting those in favour and those against.
We analysed the responses and advised the project team on the issues being raised locally. That feedback informed changes to the scheme, including removing solar panels from certain fields and introducing additional buffer zones. Landscape screening and biodiversity measures were also strengthened.
Strawberry Solar Farm subsequently secured planning consent through delegated powers, without the application needing to go before the Planning Committee.